Q2 2026 Update

US Power Equipment Lead-Time Tracker

Quarterly data on US distribution transformers, MV switchgear, dry-type, gensets, ATS, and UPS. Industry backlog vs. Teraplex delivery windows.

Q2 2026 · Data updated April 2026

Equipment Industry (weeks) Teraplex (weeks)
Distribution transformers 60–100+ 24–34
MV switchgear (6–35 kV) 52–78 12–18
LV switchgear (≤6300A) 26–52 10–16
Dry-type transformers 36–60 8–14
Containerized gensets 20–36 6–12
ATS / transfer switches 16–30 4–8
UPS systems 12–24 4–8

Industry figures sourced from published lead-time surveys, distributor quotes, and procurement-team reports. Q2 2026 snapshot.