Power and connectivity
Confirm available service, energization timing and network connectivity. The GB300 reference uses an approximately 3 MW gross facility interface per cluster.
Turnkey compute.
Deployed within 180 days.
A modular data center for AI, with power, cooling and rack infrastructure integrated before delivery.

Build and test the cluster.

Prepare foundations, power and connectivity.

Then deliver, connect and commission.

Rack positions and service access are planned as one layout, with space for equipment installation and ongoing maintenance.
Overhead A/B busways bring distribution into the enclosure, aligning power connections with the rack layout before delivery.
Supply and return headers bring liquid cooling to the rack row, with interfaces coordinated for the selected rack platform before site connection.
Add Alpha clusters as power and demand grow. Plan the first phase around your workload, then reserve land, electrical capacity and cooling connections for expansion.

Confirm available service, energization timing and network connectivity. The GB300 reference uses an approximately 3 MW gross facility interface per cluster.
Allow space for the cluster, external cooling plant, delivery vehicles, lifting and maintenance. Reserve the land and interfaces needed for later phases.
The reference design uses liquid cooling and dry heat rejection. Hot conditions can require adiabatic assist using stored water; storage and replenishment follow the site climate.
Set the rack platform, sustained load, redundancy and operating requirements. Final equipment interfaces and local approvals are part of project engineering.
Share your target capacity, location and timing. We’ll review your site and capacity requirements, identify open questions and recommend who should join the engineering discussion.
Review the GB300 reference below, or open the product overview for the system scope, site inputs and delivery sequence.
Electrical peak, thermal design and heat rejection duty describe different reference conditions. Project engineering must reconcile them for the intended sustained load. Installed feeder capability is not simultaneous IT consumption.
View technical overview